JG Afrika | Delivering world-class road infrastructure on the N4

The construction of the second carriageway of the Bakwena N1N4 Toll route by JG Afrika (Pty) Ltd, a 100-year-old leading multi-disciplinary consulting engineering company, and a Joint Venture (JV) between Raubex and Enza Construction was completed in October 2021. The upgrade has improved the user experience and provides a safe connection between the platinum belt in the North-West and the economic hub of Gauteng, while also ensuring the efficient movement of goods and people between South Africa and Botswana.

JG Afrika has been involved in the project since 2016 when the firm was appointed to undertake the preliminary design of the second carriageway of the N4 between Ga-Rankuwa in Pretoria and Brits in the North-West. The project then progressed to detailed design and procurement with the Raubex/Enzo JV being awarded the R500 million construction contract. JG Afrika were also entrusted with supervising the construction works which commenced in March 2018.

The project included the construction of 28 km of the new eastbound carriageway of the N4 Toll Road. To accommodate the second carriageway five road bridges were widened, two new bridges were constructed including one over the Crocodile River Bridge and seven major culverts where extended.N4 | JG Afrika

The project was an extensive undertaking that also involved a large quantity of earthworks. Most of the road is constructed on the expansive clays, which needed to be removed prior to construction of the road and replaced with rock fill. If the clay is left in situ it would have resulted in premature failure of the road. In total 724 000 m3 of rock fill was brought onto site to replace the clay material. The rock fill material was sourced from a local mine, which meant that the material did not have to be sourced from a borrow pit. This helped to lessen the environmental impact of the project.  The clay material was then spoiled in a variety of ways such as using the clay to flatten the batters and increase the safety of the road.

Emma Day, a JG Afrika Executive Associate and Highway Engineer, says that the upgrade of the N1N4 is one of the firm’s many flagship road construction projects.

N4 | JG Afrika

“We achieved exactly what we set out to do which was to deliver infrastructure of the highest possible quality to Bakwena Platinum Toll Concessionaire. This can also be attributed to excellent dynamics and clear communication channels between the engineering team, the client and the principal contracting JV, which also brought extensive skills and experience in road construction to the project,” Day says.

A highlight of the large construction project was the significant positive socio-economic impact that it had on the communities adjacent to the road in the City of Tshwane Metropolitan Municipality and Madibeng Municipality. This was achieved through extensive use of local labour and businesses.

Notably, the contractor exceeded its socio-economic and development targets on this contract. By the end of the project over 30% of the construction value had been allocated to work completed by local targeted enterprises with over 56 qualifying small enterprises (QSE) or exempt micro enterprises (EME) companies being utilized. A further 10% of the construction value utilized on local labour spend.

N4 | JG Afrika

Environmental and occupational health and safety compliance formed an important part of the project with the contractor being audited on a regular basis. The Raubex /Enza JV consistently scored highly on their OH&S audits and when the COVID-19 pandemic hit, measures were put in place immediately to protect the health of all staff and allow for the continuation of the works.

The project overcame many challenges ranging from technical to social. This was achieved in no small part by the excellent team dynamic between the Engineer, the Contractor and the Client. When a problem arose, all parties came together to find a workable solution.

Day says that she is proud of JG Afrika’s ongoing involvement with Bakwena Platinum Concessionaire. “We were again also s

N4 | JG Afrika
The construction of the second carriageway of the Bakwena N1N4 Toll route by JG Afrika (Pty) Ltd, and a Joint Venture (JV) between Raubex and Enza Construction.

upported in the field by the client’s very knowledgeable engineers. They are passionate about delivering road infrastructure that will significantly improve safety and experience for road users”.

The construction of the second carriageway N4 between Ga-Rankuwa and Brits forms part of the larger upgrade to the N4, which by the end of the concession period, will result in a dual carriageway highway from Rustenburg to Pretoria. The construction of the second carriageway of the N4 will dramatically improve the safety of this route and will result in improved economic connectivity between the regions.

 

Terms & Conditions and the POPI Act Agreement Consent Declaration

Terms & Conditions:
JG Afrika (Pty) Ltd (“the Company”) hereby advise and confirm with you that by accessing or using our website, you acknowledge, understand and agree that all information provided by you may be used and processed by JG Afrika (Pty) Ltd. The Company will not share any personal information provided by you with a third party. Personal information collected will be used for the purposes of compiling a database from which the Company may source possible applicants for future opportunities within the Company.

The Company will take all reasonable precautions to ensure the security of all information provided by you.

Please note that by submitting information via this website, you consent to the collection, collation, processing, and storing of such information and the use of such information by the Company.

POPI Act Agreement and Consent Declaration:
I hereby declare and confirm that I, as the person providing information, hereby irrevocably agree and understand that any/all information supplied or given to JG Afrika (Pty) Ltd (” the Company”) is done so in accordance with the terms and conditions late out in this agreement and consent declaration.

I hereby agree and confirm and acknowledge that:
1.The Company may use and process all my information and/or personal data in accordance with the Protection of Personal Information Act for the purpose of compiling a database from which the Company may source suitably qualified and experienced candidates for possible opportunities within the Company.
2. The Company will possess and will continue to possess my information that may be classified or may be deemed as private, confidential or as personal information.
3. All information provided by me, whether personal or otherwise, may be used and processed by the Company.
4. I have read all of the terms and conditions and consent declaration. I understand and agree to be bound by the terms and conditions as set out in this agreement.
5. I understand that I may request my personal information to be updated and/or deleted by the Company by sending an email request to [email protected].