KwaNobuhle Area 11 – Link Sewer project showcases wastewater engineering expertise

The technically-complex KwaNobuhle Area 11–Link Sewer project at Uitenhage in the Eastern Cape still stands out as a sound example of the extent of JG Afrika’s skills and capabilities in wastewater engineering.

Construction of retaining wall fill reinforcement using geogrids and G7 material | JG Afrika

New infrastructure
We were appointed by the Nelson Mandela Bay Municipality (NMBM) to provide civil engineering consulting services, including design, contract administration and site supervision, for the project.  The new infrastructure supplements the capacity of an existing sewer pipeline that had reached its full capacity and could no longer cater to the increase in sewerage from rapidly expanding housing developments in-and-around KwaNobuhle.
Velisani Nyoka, a JG Afrika technologist, says that the sewer pipeline discharges to the KwaNobuhle Wastewater Treatment Works (KWWTW), located north-east of this large township on the outskirts of Uitenhage, Eastern Cape.
“The pipeline is approximately seven kilometres in length and comprises mainly unplasticised polyvinyl chloride heavy-duty pipe sections. High-density polyethylene plastic pipe was installed at the road crossings using pipe-jacking technology to minimise the impact of construction activities in built-up areas. Ductile pipes were used to cross a valley, with these 50 m-long sections installed on top of four 600 mm x 400 mm concrete columns,” Nyoka says.

Terrain challenges
One of the challenges in constructing the pipeline was the varying gradients of the terrain through which the pipeline traverses. They ranged from 0,25% to two percent in the flat areas and between two percent and 12% in the steep regions. It was, therefore, impossible to use deep excavations in the very steep sections to prevent high velocities.

An eight-metre-high and 250 m-wide gabion/ Terramesh retaining wall was The completed gabion/ Terramesh retaining wall | JG Afrikabuilt along the severely eroded and unstable embankment between KwaNobhule South and North.
This structure protects both the new and old pipelines that run along the river during heavy rains, while also successfully addressing previous environmental and public safety concerns.

Unsuitable material was cut back at an average length of eight metres from the face of the existing embankment. Using an excavator, about 7 300 m3 of material was removed during this stage of the construction of the wall.
The 3m x 3m x 1m Terramesh baskets were then installed on an in-situ concrete foundation that was built along the embankment to create a robust wall. It features a step of about two metres in height and 0,5 m sideways along the entire length of the face to the final level.
Nyoka says that the Terramesh baskets were placed on geogrids that were spread throughout the area that received G7 material. The geogrids were positioned at two metre heights of the fill material, with the geotextile membrane placed underneath and at the back of the boxes for filtration purposes and to prevent the loss of fines.
Perfectly laid sewer pipeline awaiting selected fill blanketMacdrains were then installed along the full length of the embankment for drainage purposes.
Spread across the 70 degree-angled slope of the embankment, they separate the fill and in-situ material to enable seepage water to drain down to the 110 mm-diameter perforated pipes.
The water is then drained out of the wall via transverse pipes that were installed at 50 m intervals along the length of the face.
Security fence and guard rails were also installed in front of the wall as further protection measures.
This labour-intensive construction method provided many employment opportunities for members of surrounding communities.

Employment opportunities
A total of 18 small, medium and micro enterprises from various wards of the NMBM were also sub-contracted by the principal contractor to build the retaining wall.
The project, it was delivered according to standard, drawing and specification – a feat he attributes to outstanding participation of all members of the professional team right from the outset.

 

Terms & Conditions and the POPI Act Agreement Consent Declaration

Terms & Conditions:
JG Afrika (Pty) Ltd (“the Company”) hereby advise and confirm with you that by accessing or using our website, you acknowledge, understand and agree that all information provided by you may be used and processed by JG Afrika (Pty) Ltd. The Company will not share any personal information provided by you with a third party. Personal information collected will be used for the purposes of compiling a database from which the Company may source possible applicants for future opportunities within the Company.

The Company will take all reasonable precautions to ensure the security of all information provided by you.

Please note that by submitting information via this website, you consent to the collection, collation, processing, and storing of such information and the use of such information by the Company.

POPI Act Agreement and Consent Declaration:
I hereby declare and confirm that I, as the person providing information, hereby irrevocably agree and understand that any/all information supplied or given to JG Afrika (Pty) Ltd (” the Company”) is done so in accordance with the terms and conditions late out in this agreement and consent declaration.

I hereby agree and confirm and acknowledge that:
1.The Company may use and process all my information and/or personal data in accordance with the Protection of Personal Information Act for the purpose of compiling a database from which the Company may source suitably qualified and experienced candidates for possible opportunities within the Company.
2. The Company will possess and will continue to possess my information that may be classified or may be deemed as private, confidential or as personal information.
3. All information provided by me, whether personal or otherwise, may be used and processed by the Company.
4. I have read all of the terms and conditions and consent declaration. I understand and agree to be bound by the terms and conditions as set out in this agreement.
5. I understand that I may request my personal information to be updated and/or deleted by the Company by sending an email request to [email protected].