FIBRE-OPTIC CABLE ENVIRONMENTAL IMPACT ASSESSMENT

We were appointed by Sirius Access Solutions to undertake the basic environmental impact assessments for its fibre-optic duct infrastructure.

The standard construction method involves rapid trenching and cables installed using mechanical methods.

In sensitive areas where trenching was not feasible, horizontal directional drilling was deployed.

The network was developed along the N6 between Aliwal North and East London; the N2 between East London and Port Elizabeth; and the N2 between Port Elizabeth and George.